This is your logbook. Insert here all relevant information regarding the evolution of your project
During this week we managed to:
This week was mainly devoted to creation of material list. We also made several changes to the construction of solar algae dryer. Those changes are:
We also started to work on detailed scheme of our device.
Easter Holiday Week
1.Environment:
2. Dimensioning:
3. Budget:
4. Design:
5. Framework:
6. Technology
7. Marketing
8. Free questions
9. Conclusion
- Build a solar dryer that takes out the water and leaves the algae (90% algae, 10% water)
- Prototype about 5l, adapt to 40-60l tanks
- Temperature can't be higher than 50° C
- 500€ budget to start with
- built of reused materials, materials from ISEP, then identify what else materials we need → find a shop → ask for offer.
- Design, solar panel, temperature control.
- should operate in -5° - 40° C
- should have a main switch, simple display (temperature)
- considering also others interested in this product, fashionable right now in the bio market.
- Reproducible
Interim presentation
Please register here all project activities
| Start | End | Task | Description | Who |
|---|---|---|---|---|
| 2013-03-01 | 2013-03-03 | Choose the project topic | Team 1 | |
| 2013-03-05 | 2013-03-05 | Wrote agenda for the first meeting | Team 1 | |
| 2013-03-07 | 2013-03-07 | First supervisor meeting | Changed the project to solar dryer | Team 1 |
| 2013-03-09 | 2013-03-09 | Gantt chart and task allocation | Sven, Ola | |
| 2013-03-11 | 2013-03-11 | Meeting about different drying methods and research,writing week reports | Paul,Sven,Ola,Benedicte | |
| 2013-03-12 | 2013-03-12 | Setting up ethical code for teamwork | Team 1 | |
| 2013-03-13 | 2013-03-13 | Inside team meeting | Discussion over distiller | Paul,Sven,Ola,Benedicte |
| 2013-03-14 | 2013-03-14 | Supervisors meeting | Team 1 | |
| 2013-03-15 | 2013-03-15 | Laboratory experiment | Checking algae magnetic properties | Paul,Sven,Ola,Benedicte |
| 2013-03-15 | 2013-03-17 | Research | Creating first chapters of state of art | Team 1 |
| 2013-03-18 | 2013-03-18 | Meeting | Creating Box World, Material List | Team 1 |
| 2013-03-19 | 2013-03-19 | Group meeting | Agenda for 4th supervisor meeting, Work division, Discussion over different mechanisms in algae dryer | Team1 |
| 2013-03-22 | 2013-03-22 | Group meeting | Finished Material List | Paul,Bartek,Ola,Benedicte |
| 2013-04-03 | 2013-04-03 | Group meeting | Discussed and divided tasks for the next week, wrote Agenda for 5th meeting, finished material list | Paul,Ola,Sven |
| 2013-04-08 | 2013-04-08 | Group meeting | Working on seperate parts of the report, working on presentation for Energy & Sustainablility | Team 1 |
| 2013-04-11 | 2013-04-11 | Group meeting | Discussed the work plan for the next week | Team 1 |
| 2013-04-12 | 2013-04-12 | Laboratory experiment | Charging test in INEB lab | Team 1 |
| 2013-04-12 | 2013-04-12 | Group meeting | Preparing interim presentation | Team 1 |
| 2013-04-18 | 2013-04-18 | Presentation | Interim presentation | Team 1 |
| 2013-04-19 | 2013-04-19 | Project management | Made sprint for next 14 days | Paul, Sven, Benedicte |
| 2013-04-23 | 2013-04-23 | Meeting | Tasks for next weeks, discussed feedback on interim report | Paul, Sven, Benedicte, Ola |
| 2013-04-24 | 2013-04-24 | Meeting | Tried to meet with João Silva | Ola |
| 2013-04-26 | 2013-04-26 | Meeting | Discussed plexiglas problems with João Silva | Sven, Bartek |
| 2013-04-30 | 2013-04-30 | Meeting | Discussed the to do list and agenda for next meeting | Sven, Ola, Benedicte, Paul |
| 2013-05-02 | 2013-05-02 | Test | Ultra sound sensor test | Sven, Benedicte, Paul |
| 2013-05-03 | 2013-05-03 | Meeting | Discussion with Benedita | Ola, Paul, Benedicte, Sven |
| 2013-05-08 | 2013-05-08 | Test | Algae charging test | Team 1 |
| 2013-05-09 | 2013-05-09 | Test | Algae charging & ultra sound sensor | Team 1 |
| 2013-05-20 | 2013-05-20 | Test | Algae charging with amended voltage | Benedicte, Paul, Sven |
| 2013-05-21 | 2013-05-21 | Purchase | Purchasing of materials | Benedicte, Paul |
| 2013-05-22 | 2013-05-22 | Test | Ultra sound sensor with amended software | Bartek, Sven |
| 2013-06-03 | 2013-06-03 | Meeting | Meeting with João Francisco concerning assembling of the tank | Ola |
| 2013-06-03 | 2013-06-03 | Meeting | Group meeting, working on the project together | Team 1 |
| 2013-06-03 | 2013-06-03 | Assembling | Connecting wheels to the pallet | Bartek, Ola |
| 2013-06-03 | 2013-06-03 | Meeting | Benedita's advice on programming | Bartek, Ola |
| 2013-06-04 | 2013-06-04 | Meeting | Working on the deliverables | Paul, Sven, Benedicte |
| 2013-06-05 | 2013-06-05 | Meeting | Assembling the report | Sven, Paul |